Status Report Template
Last updated
Was this helpful?
Last updated
Was this helpful?
Usage Instructions
Completed by the Project Manager Delivered weekly at mutually agreed to timing (suggested is Monday or Tuesday)
Steps to complete:
Update project dashboard.
Identify high-level project narratives & value items
Update project workstream information
Project workstream examples are: modeling, configuration, integration, materials
Include delivery dates and highlight milestones
Call out any individual risks or issues related to each workstream
Compile all workstream risks & issues
Each risk or issue must have a suggested mitigation plan & estimated completion timing
Deliver via email to all project stakeholders
Internal and external stakeholders
include dashboard screenshot in body of email